Please find attached links to the latest version of the GNSO Council’s Program Suite for the meeting on 17 December 2020. Per the agenda, the Council will not review these tools in detail. However, after your preliminary review in advance of the meeting and should you find an area that you have questions or parts that need clarification, please send your questions or comments to the mailing list.
Agenda:
Key Structural Changes of the Program Suite:
- The monthly publication of the tools suite will now only include links to the Council’s wiki section. This will allow for better tracking of access to the work products from the mailing list and GNSO website. Location of the tools suite:
Key Project Changes for this Period:
- Transfer policy Issue report public comment closed 30 November with only three submissions
- IDN charter drafting team held its first meeting on 8 December
- EPDP-P2A Chair appointment pending, and first meeting scheduled for 17 December
- RPM_IGO_CRWT Chair appointment pending
- SCBO/Council submitted comment for PTI-IANA FY22 Draft Operating Plan and Budget
- IRP_IOT removed from projects list and any activities will be tracked on Council Action Items
Key Project Activities for January 2021 (ADR):
- Council to consider Transfer Policy Issue Report and possible launch of PDP
- Council expected to consider the RPM’s Phase 1 Final Report consensus recommendations
- Council briefing on SubPro Final Report
- Review EPDP-P1 IRT Wave 1 report findings and what that means for IRTs of PPSAI + T&T
- The SCBO to review ICANN Org FY22 Draft Operating Plan and Budget.