Dear all,
Please find attached links to the latest version of the GNSO Council’s Portfolio Management Tool Suite for the meeting on
15 June 2022.
Agenda:
Links to the Program Suite:
Key Program Suite Structural Changes for this Period:
- Given the activity across several communities, “IDNs” is now its own Program and distinct from the “gTLD” Program where these activities used to reside.
Key Project Changes for this Period:
- EPDP_IGO – Council to vote of EPDP’s Final Report, as deferred from May 2022.
- TPR_P1 – Release of Initial Report for public comment on 20 June.
- Small Team work: Modifying Consensus Policies, DNS Abuse, SSAD ODA, Closed Generics
- Project Packages:
Key Project/Operations Activities for July/August 2022:
- EPDP_SCRP_IGO – Consider resolution on Board Report
- RDA_ST – Assignments #1/#2 report and Project Change Request
- Modifying Consensus Policies response – small team
- GGP for select SubPro topics
- RPM_P2 – Council to consider the Policy Staff Report
- ICANN74 – Council response to GAC advice, if applicable
- EDDP_PSR – Council to consider requesting a Policy Status Report on Expiration Policies
- Council to consider CSC Effectiveness Review 2021 final report
- Council to approve full-slate of CSC members
Please let staff know if you have any questions.
Thank you.
B
Berry Cobb
Policy Development – Senior Program Manager
Internet Corporation for Assigned Names and Numbers (ICANN)