Dear All,
Please find attached the EPDP-Phase 2 Project package that closes out April of 2020.
The project health remains on a “Revised Schedule” and “On-Target”. The percent complete reports at 94% with an 88% elapsed time (to 30 June 2020) from when the project started. Percent complete is up only 2% from last period due to mostly administrative tasks.
You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg
Thank you.
Berry Cobb
@berrycobb
GNSO Policy Consultant
_______________________________________________
Gnso-epdp-team mailing list
Gnso-epdp-team@icann.org
https://mm.icann.org/mailman/listinfo/gnso-epdp-team
_______________________________________________
By submitting your personal data, you consent to the processing of your personal data for purposes of subscribing to this mailing list accordance with the ICANN Privacy Policy (
https://www.icann.org/privacy/policy) and the website Terms of Service (
https://www.icann.org/privacy/tos). You can visit the Mailman link above to change your membership status or configuration, including unsubscribing, setting digest-style delivery or disabling delivery altogether (e.g., for a vacation), and so on.