Dear GNSO Council,
On behalf of the IGO WT leadership team, please find a link to the IGO WT’s 31 July 2021 project package.
Link: https://community.icann.org/x/FwDQCQ
- Page 01 – Summary timeline
- Page 02 – Project Sitrep – an extract from the Council’s Project List
- Page 03 – Group roster
- Page 04 – Group attendance for plenary
- Page 05 – Work and activity metrics
- Page 06 – Project Plan, Gantt chart
- Page 07,8 – Work plan & Action items for the period
Key points:
- As you will recall, the PCR was accepted by the GNSO Council and as a result, the WG key deliverable dates shifted five weeks out.
- The delivery of the Initial Report for public comment is scheduled for 07 Sep 2021.
Please let us know if you have any questions.
Thank you
B
Berry Cobb
GNSO Policy Consultant
Principal |
BAC in Black Consulting [bacinblack.com]
Mob:
+1 (720) 839-5735
[twitter.com]