Good morning/afternoon all.

 

Thanks to everyone who contributed to this document. I have reviewed it and it looks good. I added a few suggested edits in the attached.

 

Let me know if you have any questions about my proposed edits.

 

Best,

Keith

 

From: CSC-Review [mailto:csc-review-bounces@icann.org] On Behalf Of Bart Boswinkel
Sent: Friday, December 08, 2017 4:03 AM
To: CSC-review@icann.org
Subject: [EXTERNAL] Re: [CSC-Review] CSC Review Team Notes, 16 November

 

Dear all,

Please find included the latest version of the consolidated comments on the CSC charter, including Martin’s additional comments

@ Keith: could you be so kind to look at document?

Kind regards,

Bart

 

 

From: CSC-Review <csc-review-bounces@icann.org> on behalf of Martin Boyle via CSC-Review <CSC-review@icann.org>
Reply-To: Martin Boyle <martin.boyle.hertford@ntlworld.com>
Date: Friday 24 November 2017 at 01:06
To: Maria Otanes <maria.otanes@icann.org>, "CSC-review@icann.org" <CSC-review@icann.org>
Subject: Re: [CSC-Review] CSC Review Team Notes, 16 November

 

I think that item 4 was for me to comment on Donna’s comments:  just missed completing the attached in time!

 

From: CSC-Review [mailto:csc-review-bounces@icann.org] On Behalf Of Maria Otanes
Sent: 17 November 2017 17:34
To: CSC-review@icann.org
Subject: [CSC-Review] CSC Review Team Notes, 16 November

 

Dear CSC Review Team,

 

Attached, please find notes from yesterday’s call. Next Steps can be found below.

 

Have a wonderful weekend,

Ria

 

----------

Timeline for next steps

Who ?

What?

When to be completed?

Abdala, Keith

provide comments on charter

20 November

Donna

provide high level description of issues

21 November

Bart

description of process, ToR and basic info

22 November

Martin

Check description Donna

23 November

Bart

Detail high level issues identified using comments document

24 November

Donna, Bart

Prepare draft initial CSC report

1 December

Donna, Abdala

Consolidate changes to charter

1 December

Martin, Keith

Comment initial draft CSC review team report

6 December

CSC review team

Discuss report and

7 December

Bart

Consolidate proposed changes

8 December (by 17.00 UTC)

Donna

Finalise report ad send draft to CSC

8 December

CSC review team

Meeting with CSC to discuss draft findings

14 December 20.00 UTC