CWG IANA meeting #39 on 14 April at 10:00 UTC

Notes
Seun Ojedeji on audio only at this time.

Opening Remarks

Chairs have change the order of the questions on the 'Punch List'
Question 9 deals with 'which variant' --> sounds like the group is leaning torward legal entity
With legal entity, if there were ever bankruptcy at ICANN, it would not necessarily affect PTI
The entity can be sued (each party can be)

Poll for the group (to get sense of the room):
Which variant is preffered?
- legal separation (56.5%)
- functional separation (21.7%)
- undecided (21.7%)

---> direction for Question 9: legal separation variant preference 

Question 6: Accountability on ICANN/PTI Contract 
Periodic Review could trigger separation
- address accountability in contract? yes, relevant (but details need to be worked out)
- address through PRF and/or CSC? the PRF can review the contract/SOW, but does not hold contract. The CSC is also a review/performance management structure. 
- Are other means required? The CCWG will enhance ICANN's accountability mechanisms and these will be important to structure.

Question 1: What role for PTI Board?
Insider board agreed on, subject to other new structures withstanding stress tests. And comprehensive contract.

Edit (staff/DT-N): change the term 'Periodic Review Team' to something like 'IANA Review Team'.