Dear All,
Please find attached the EPDP-Phase 2 Project package that closes out April of 2020.
The project health remains on a “Revised Schedule” and “On-Target”. The percent complete reports at 94% with an 88% elapsed time (to 30 June 2020) from when the project started. Percent complete is up only 2% from last period due to mostly administrative tasks.
You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg
Thank you.
Berry Cobb
@berrycobb
GNSO Policy Consultant