Dear All,

 

Please find attached the EPDP-Phase 2 Project package that closes out March of 2020.

 

The project health remains on a “Revised Schedule” and “On-Target”. The percent complete reports at 92% with an 81% elapsed time from when the project started. This is up 11% from last period due to the close of the public comment period, close out of tasks related to Priority 2 items and completion of staff related tasks. Do not let the 8% remaining fool you. We have a fair amount of comments to review, review comments from the Addendum report, form final agreements on proposed recommendations, perform a consensus call, and review the text of the Final Report.

 

You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg

 

Thank you.

 

 

 

Berry Cobb

@berrycobb

GNSO Policy Consultant