Dear All, Please find attached the EPDP-Phase 2 Project package that closes out February of 2020. The project health remains on a "Revised Schedule". The percent complete reports at 81% with a 75% elapsed time from when the project started. This is up 8% from last period due to days expired for the public comment and the closeout of preliminary tasks for Priority 2 items. The public comment period closes 23 Mar. 2020. You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg Thank you. Berry Cobb @berrycobb GNSO Policy Consultant