For your information, below is the time-line for the Report from now until (hopefully) Board adoption. If you have any further question, please don’t hesitate to get in touch.
Council Vote – 16 October
Opening Public comment – 20 October
Closing Public Comment – 10 November October (21 days)
Opening Reply Period – 10 November
Closing Reply Period – 1 December (21 days)
Submission of 'GNSO Council Report to the ICANN Board’ to the GNSO Council – 1 December
Consideration of 'GNSO Council Report to the ICANN Board' by GNSO Council - 11 December
Submission of 'GNSO Council Report to the ICANN Board' – 12 December
Possible ICANN Board meetings to consider the recommendations: mid January 2015 / ICANN 52 in Marrakech