All,
Please see a note sent by Flip (our GNSO Council Liaison) to the Council with an update on SubPro. You will see a proposal in that note for a slight modification of the timeline as follows:
|
Potential Modified Work Plan |
|
17 Dec 20 - Content Freeze |
|
22 Dec 20 - Consensus Call Begins |
|
8 Jan 21 – Consensus Call Ends |
|
11 Jan 21 – Consensus Call Designations |
|
12 Jan 21 – WG call to discuss designations |
|
13 Jan 21 – Challenges to Consensus Call Designations |
|
18 Jan 21 – Minority Reports Due & Deliver Report to the Council |
|
21 Jan 21 – GNSO Council Meeting |
Please note that this schedule needs to get the ok from the Council before we make it official.
We will discuss further on our Thursday call (which will be after the Council meets).
Sincerely,
Jeff
|
|
Jeffrey J. Neuman Founder & CEO JJN Solutions, LLC p: +1.202.549.5079 http://jjnsolutions.com |
From: council <council-bounces@gnso.icann.org> On Behalf Of
Flip Petillion
Sent: Wednesday, December 16, 2020 5:18 AM
To: GNSO Council List <council@gnso.icann.org>
Subject: [council] Next Council Meeting 17 December 2020 - Sub Pro WG Status & Proposed New Timeline
All,
Below is new timeline proposed by the Sub Pro Leadership.
In my opinion, these new proposed extensions are quite reasonable and realistic.
They allow the discussion of
the Final Report during the GNSO Council Meeting in January. Leadership expects the Council
will have 1)
the consensus designation prior to the Document Deadline for the January meeting (which is 11 January), and 2)
the minority reports (If any) before the January meeting itself.
The plan is to
present this
for a vote during the February Council Meeting. If asked for, we may consider to organize
a more in-depth discussion of the report after our January Council Meeting, before
the vote in February.
Let me remind that the Draft Final Report was published last Summer out for comment. It was the result of 5 years of discussions. I have witnessed that Sub Pro Leadership has
been providing the Working Group with
several drafts. The Working Group members have been given an opportunity to
comment and their comments have been shared among the participating members.
The latest drafts contain minor clean ups.
I add my personal gratitude to Staff. Without their relentless support, this was impossible to achieve.
The new
timeline is a
positive response to
people asking for more time. The timeline
will give them
extra days to express support/non-support for the report. It will also add
an extra 10 days for the
minority
report(s).
|
Council Approved Work Plan |
Work Plan Announce Last Week |
Potential Modified Work Plan |
|
17 Dec 20 – Consensus Call |
17 Dec 20 – Content Freeze |
17 Dec 20 - Content Freeze |
|
23 Dec 20 – Final Report delivered to Council |
22 Dec 20 – Consensus Call Begins |
22 Dec 20 - Consensus Call Begins |
|
|
5 Jan 21 – Consensus Call Ends |
8 Jan 21 – Consensus Call Ends |
|
|
6 Jan 21 – Consensus Call Designations |
11 Jan 21 – Consensus Call Designations |
|
|
7 Jan 21 – WG Meeting to discuss designations |
12 Jan 21 – WG call to discuss designations |
|
|
8 Jan 21 – Challenges to Designations and Minority Reports Due |
13 Jan 21 – Challenges to Consensus Call Designations |
|
|
11 Jan 21 – Deliver Final Report to Council |
18 Jan 21 – Minority Reports Due & Deliver Report to the Council |
|
|
21 Jan 21 – GNSO Council Meeting |
21 Jan 21 – GNSO Council Meeting |
In sum, with this
modified timeline
(column to the right), the Final Report with Consensus Designations
can be sent by the Document Deadline of 11 January 2021.
Sub Pro Leadership expects the minority
reports (fin any) to be
available to the Council by the time
of the discussion of
the report during the January Meeting.
I look forward to our next Council meeting on Thursday.
Best regards,
Flip