Thanks
Alissa,
I’m
afraid that I will not be able to join next week’s call (it will be during my
night and I am driving the following morning early). I am also away on
holiday from tonight until Tuesday late. So I thought it might be useful
to put down just a couple of comments on the timeline.
I
am basing my points on the optimised sheet. I welcome what you are trying
to do so that we have a real sense of delivery by end September. I do not
feel greatly convinced…
We
obviously do need to show substantive progress by end of September. At the
least, we ought to be able to say to NTIA and more widely:
1.
This
is the direction of travel
2.
These
are the pieces that need to be finalised
3.
This
is the timescale for those pieces to be delivered.
4.
So
this is when the transition could be finalised (and then there is also the
implementation period – the more complicated our solution, the longer that stage
will take).
On
specific points, I am concerned with the way this schedule deals with the two
consultation periods. I’m not sure that the first looking at the IETF
& RIR pieces and the second the full works really works for me and 15 days
for this second one seems unrealistic. Yes, interested parties will only
just have gone through the consultation period, but in fact what we will be
looking for here is how the different elements will bed together. So
shouldn’t we really be looking at step 4.1 ending end week 1 August, all
subsequent steps shifting right two blocks and then an iteration for a second
consultation to closure as per the previous timescale?
We
should also look some time after delivery of the CWG input into the timescale to
prepare the right material for NTIA for end September (or more correctly
beginning of October when they can start to work on it
again).
Thanks
and have a good call next week.
Martin
From:
internal-cg-bounces@icann.org [mailto:internal-cg-bounces@icann.org] On
Behalf Of Alissa Cooper
Sent: 19 February 2015 16:44
To:
ICG
Subject: [Internal-cg] Draft agenda for Feb 25
teleconference
Here is a proposed agenda for the teleconference we are
currently doodling about for next week. Please comment.
(1) Minutes approval for F2F meeting Feb 6-7
(minutes should be available for review this
week)
(2) ICG timeline discussion
Objective: Decide on our timeline going forward so that we
can publish an updated timeline. See this thread: <http://mm.icann.org/pipermail/internal-cg/2015-February/002969.html>.
(3) Discussion of responses to question posed to IETF and
RIRs
(assuming we receive responses by Feb
21)
(4) Begin Step 2 assessment of IETF and RIR proposals in
combination
See this thread: <http://mm.icann.org/pipermail/internal-cg/2015-February/003049.html>
Thanks,
Alissa