Hi all, I am sharing here the project package from EPDP phase 2. Please let me know if you have any question. Best, Rafik ---------- Forwarded message --------- De : <policy@bacinblack.com> Date: jeu. 9 janv. 2020 à 05:03 Subject: [Gnso-epdp-team] December 2019 - EPDP-P2 Project Package To: <gnso-epdp-team@icann.org> Dear All, Please find attached the EPDP-Phase 2 Project package that closes out December of 2019. The project health has returned to “On-Target” with a “Revised Schedule” after the GNSO Council reviewed the revised project plan at its December meeting. The percent complete reports as 59% complete with a 63% elapsed time from when the project started. As a reminder, our Initial Report is due no later than 7 Feb. 2020 with a Final Report delivery date of 11 Jun. 2020. You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg Thank you. B Berry Cobb @berrycobb GNSO Policy Consultant