EPDP Project Package - 31 Mar. 2020
![](https://secure.gravatar.com/avatar/c46b69e4a3e4a166b41db5af5d0e4ee8.jpg?s=120&d=mm&r=g)
Dear All, Please find attached the EPDP-Phase 2 Project package that closes out March of 2020. The project health remains on a "Revised Schedule" and "On-Target". The percent complete reports at 92% with an 81% elapsed time from when the project started. This is up 11% from last period due to the close of the public comment period, close out of tasks related to Priority 2 items and completion of staff related tasks. Do not let the 8% remaining fool you. We have a fair amount of comments to review, review comments from the Addendum report, form final agreements on proposed recommendations, perform a consensus call, and review the text of the Final Report. You can find separated work products on the wiki: https://community.icann.org/x/6BdIBg Thank you. Berry Cobb @berrycobb GNSO Policy Consultant